Analysis of the design of concrete and concrete scuppers on metal piles on embankment of residential buildings on drilling ground
Abstract
Analysis of the design of concrete and concrete scuppers on metal piles on embankment of residential buildings on drilling ground
Incoming article date: 23.12.2024The article shows calculation on the arrangement of the embankment and the design of reinforced concrete casings on metal staves for stairs. The dam boundaries are located on the territory of a residential complex with a large difference in height. The ground base is prosaic. Calculation of transfer of the soil from II type of drilling to I type by tamping method, which will ensure the strength and reliability of the body of the fill. Constructive actions to ensure resilience are described. The metal piles with forced connecting link and reinforced concrete coaxes in the form of a beam system have been designed.
Keywords: a mound, drilling ground, improvement, dense urban development, sediment, density of the ground, collapse prism, sliding radius, the method of ramming, sling